M27 closure: Which part of the motorway is shut, how long for and what is the diversion route?
A major stretch of motorway is closed over Christmas and new year - so that a new junction can be built.
The traffic cones are out and as of this morning (December 24) the M27 is closed in both directions, thanks to a massive project between National Highways and Hampshire County Council.
Over the next week, an 8,500-tonne underpass is being moved into position to create a new junction for the £100m Welborne Garden Village development, which will have 6,000 new homes when completed.


A spokesperson for the county council said: “[The project includes] the creation of a new dual carriageway, with four roundabouts, to link the slip roads to the existing road network, forming a 'free flowing link' at junction 10.”
Here is everything you need to know about the M27 closure - and when the motorway will reopen.
Which part of the M27 is closed?
The motorway has been closed off between junction 11 for Fareham and junction 9 for Whiteley.
The rest of the M27 will be operating as normal throughout the festive period - although there are still roadworks elsewhere to contend with.
When will the M27 reopen?
Having closed this morning, the M27 will be shut for the next two weeks.
National Highways hopes to reopen the motorway at 4am on January 4, although this is subject to change depending on the progress made with the underpass.
What is the diversion route?
Instead of driving between junctions 9 and 11, motorists will be diverted towards the A27 instead.
A 5.9 mile diversion takes drivers past Segensworth, Titchfield and Fareham, before reaching the junction 11 roundabout to get back onto the M27.
It’s a route that ordinarily takes 15 minutes, compared to 10 minutes on the motorway - but that doesn’t account for the mass of extra traffic that will be using this stretch of road.
Motorists are advised to allow for at least an extra 30 minutes on their journeys, just in case traffic is really bad.