Popular beach in Wales to close for months while multi-million pound coastal defence scheme undertaken
A beach in Wales will be closed for months while a multi-million pound coastal defence scheme is undertaken.
The defence scheme in Conwy is due to get underway at the end of the month. Up to 80,000 tonnes of rock from North Wales quarries will brought in for the works between Towyn and Kinmel Bay.
The rocks will be used to strengthen an existing revetment between the two communities. A sea wall will also be raised by 50cm-75cm as the current wall wasn’t designed for projected sea level rises and increased storminess.


The contractor, Jones Bros, will start setting up a compound on the promenade car park on Monday, September 30, and begin construction work a fortnight later. The scheme is expected to be completed by spring 2026.
During construction, the beach will be closed and some areas will remain off-limits for the scheme's duration. Conwy Council said the closure was ordered for safety reasons and the beach will be “re-opened in phases”.
Safety improvements are on the agenda too, with a proposed new crossing point by Rhyl Harbour Cafe designed to make the pedestrian and cycle route from Kinmel Bay to Rhyl safer. The scheme costs have been set at £13m but Conwy Council is paying 15% of this. The rest has been sourced from the Welsh Government’s Coastal Risk Management Programme.